The City Council is considering a first amendment to the contract with G2K Construction for the modernization of the Senior Center. The project's initial phase revealed significant issues, including a deteriorated plumbing system and main sewer line, requiring additional funding. Staff recommends approving the contract amendment, re-appropriating funds, and authorizing the use of various funds to complete the project. The total not-to-exceed project cost is $6,181,583. The modernization aims to address repairs, improve accessibility, and provide enhancements to reduce future construction costs.
Details
- Subject
- Senior Center Modernization
- Summary
- The City Council is considering a first amendment to the contract with G2K Construction for the modernization of the Senior Center. The project's initial phase revealed significant issues, including a deteriorated plumbing system and main sewer line, requiring additional funding. Staff recommends approving the contract amendment, re-appropriating funds, and authorizing the use of various funds to complete the project. The total not-to-exceed project cost is $6,181,583. The modernization aims to address repairs, improve accessibility, and provide enhancements to reduce future construction costs.
- Report Date
- 2026-02-02
- Report Type
- staff
- Report Title
- G2K Construction First Amendment for Senior Center Modernization
- Authoring Body
- City of Azusa, Department of Community Resources
- Reporting Period
- 2025-2026