unclassified
Funding Allocation Corrections for Pine Avenue Connector (ST061) and SR-71 Interchange Improvements (ST204) Projects
May 20, 2025 · Chino, CA
📄
Source: Source Document
(PDF, 3 pp)
Retrieved May 3, 2026
from chino.legistar1.com ↗
Confidence:
80%
Medium
Summary
This report documents funding allocation corrections for the Pine Avenue Connector and SR-71 Interchange Improvements projects. The corrections were identified during a reconciliation of expenditures and include the reallocation of approximately $1.8 million in costs to the Measure I Arterial Fund. The report also details the final funding allocations for the Pine Avenue Connector Project, which will be officially closed out as of June 30, 2025. The City will continue efforts under the successor project, Pine Avenue Connector / Bridge Project (ST261).
Details
- Subject
- Funding Allocation Corrections for Pine Avenue Connector (ST061) and SR-71 Interchange Improvements (ST204) Projects
- Summary
- This report documents funding allocation corrections for the Pine Avenue Connector and SR-71 Interchange Improvements projects. The corrections were identified during a reconciliation of expenditures and include the reallocation of approximately $1.8 million in costs to the Measure I Arterial Fund. The report also details the final funding allocations for the Pine Avenue Connector Project, which will be officially closed out as of June 30, 2025. The City will continue efforts under the successor project, Pine Avenue Connector / Bridge Project (ST261).
- Report Date
- 2025-05-20
- Report Type
- corrective memorandum
- Report Title
- Corrective Memorandum - Reconciliation and Funding Allocation for Pine Avenue Connector (ST061) and SR-71 Interchange Improvements (ST204)
- Authoring Body
- Department of Public Works
- Reporting Period
- 2020-2025