The resolution approves Change Order 1 for the Lakeside Sewer Lining Project, increasing the contract by $25,281.93 to raise three additional manholes. This change is recommended by city staff to ensure accessibility in case of a sewer backup. The funding will come from the Sewer Utility Fund 604.
Details
Subject
Lakeside Sewer Lining Project (2021-14) Change Order 1
Summary
The resolution approves Change Order 1 for the Lakeside Sewer Lining Project, increasing the contract by $25,281.93 to raise three additional manholes. This change is recommended by city staff to ensure accessibility in case of a sewer backup. The funding will come from the Sewer Utility Fund 604.